Mercator - Horta
Project Details
Dates: 2018-2019
Builder: Elia
Client: Omexom
Project scale: > €20 million
Context
TR42026 - L-380 Mercator-Horta Upgrade HTLS Lineworks. The 380kV Mercator-Horta lineworks project involves replacing 2 sets of wires with old AMS conductors with high-performance HTLS conductors between Zomergem and Kruibeke.
The 380 kV high-voltage line runs over a distance of about 50 km, through 12 municipalities and towns in the province of East Flanders.
For more information see: http://www.elia.be/nl/projecten/netprojecten/Brabo
Challenges
Planning: a lot of work in very short timeframes
Coordination with headquarters in Germany.
The role of hop
Hop is taking on the task of overall project management for this project on behalf of Omexom Germany. Hop provides the complete project management team here. Following tasks are part of our package:
General project management execution
Controlling subcontractors
HSEQ
Planning
Method statements
Project strategy
Financial management