Context

Partial replacement and/or reinforcement of 13 pylons in the line 70kV Tienen-Heverlee IN324. This was necessary due to the end of life of part of the line.

Challenges

To combine the input of different departments of Elia as an external agency in one tender file.

The role of hop

Based on an earlier audit, it was decided that a number of pylons needed to be replaced or reinforced. Hop provided the preliminary study and drafting of the specifications. Some possible working methods were proposed with an analysis of the bottlenecks.

Clear communication and coordination was crucial.
 
Tienen-Heverle.jpg

Partners

Elia Group
 

hop is ready to support your project

Do you have an energy project in development?
We would be happy to explore how we can assist.

Get in touch
Vorige
Vorige

BSTOR - Feasibility studies, grid connection, cost estimation, pre-engineering

Volgende
Volgende

Elia - Energy Transportation - Mercator - Horta