70kV Jodoigne - Tienen

Project Details

  • Builder: Elia

  • Client: Elia

  • Project scale: €500,000

Context

TR-42257 - L-070-JODOI-TIENE-Reconstruction P53 & P54

Rehabilitation 70kV line Jodoigne - Tienen after a summer storm. Mast assembly, reinforcements and conductor pulling P51-P55 and demolition of emergency line.

Challenges

Within this project, hops is responsible for the coordination of several contractors within the execution of the restoration of this 70kV line. An extra point of attention within this project was the sensitivity of stakeholders in the area because of the damage caused to orchards by the storm.

The role of hop

As project leader for Elia, hops supervises the correct execution of the work by the contractor(s). In doing so, we pay due attention to work preparation, proper planning and safety procedures.

Involving and coordinating with stakeholders was one of the success factors within this project.
 
70kV Jodoigne-Tienen-1.jpg

Partners

 

Do you have a project and do you want to talk to us about it?

Vorige
Vorige

Centrica battery storage Ostend

Volgende
Volgende

BSTOR: feasibility studies, grid connection, cost estimation, pre-engineering